Commercial development
New build

Innovations

ADCO resequenced the civil works to accommodate CRC coating of the structures and to avoid work in the UG Process chamber being executed as a Confined Space.

Scope

ADCO were awarded 2 recent contracts at BMS. One of the significant plant upgrades involves the implementation of a new Captured Process Waste System consisting of:

CRC Coated Concrete Bund to house the Installation of a 128,000 Litre GRP External Waste Collection Tank including stair access to top of tank and associated instrumentation and controls, Installation of new piperack & connection to existing piperack, RC Loading Bay including kerbing, traffic island and road markings, RC Underground Tank & Valve Chamber, Stainless Steel Process Drainage, Stormwater Drainage, Ducting, Footpaths and Landscaping.

Project Value

€600k

Project Duration:

16 weeks

Designers

DPS & Jacobs